Adapted and summarised from Worsley and Massyn (2026), licensed under CC BY 4.0. Changes were made to shorten and restructure the original text.
The article examines why stakeholder management becomes particularly difficult in public infrastructure projects. Based on three projects in Cape Town, the authors identify indicators that help project managers determine when more intensive and adaptive stakeholder engagement is required.
Infrastructure project success depends not only on technical delivery but also on how early and accurately the project team recognises stakeholder interests, power and relationships. Underestimating these factors can lead to conflict, delays, reduced benefits or project termination.
The authors define stakeholder complexity as the extent to which stakeholder diversity, power, relationships and changing interactions affect a project’s ability to achieve its objectives.
Existing tools, such as the power–interest matrix and stakeholder salience model, are often applied too formally, inconsistently or too late. The article therefore addresses two questions:
- Which internal and external indicators reveal stakeholder complexity?
- How can these indicators support more targeted engagement strategies?
PMI defines a stakeholder as an individual, group or organisation that may affect, be affected by, or perceive itself to be affected by a project decision, activity or outcome.
Role-Based and Agenda-Based Stakeholders
The article places particular emphasis on the distinction between:
- Role-based stakeholders: participants acting through formal positions and responsibilities, such as sponsors, authorities, contractors and operational teams.
- Agenda-based stakeholders: participants whose involvement is driven by personal or collective interests, values, economic concerns or informal power.
Agenda-based stakeholders are generally more difficult to manage because their behaviour cannot be fully controlled through contracts, organisational structures or RACI matrices. Moreover, stakeholders initially considered peripheral can gain power, legitimacy or urgency and become central to the project.
Stakeholder analysis should be treated as a continuous process of interpreting the project environment rather than a one-time classification exercise. Project managers must monitor changing positions, emerging alliances and signals from the wider social and institutional environment.
Different stakeholder groups may also define project success differently. Managing complexity therefore requires continuous communication, alignment and adaptation throughout the project life cycle.
Three Municipal Projects in Cape Town
The authors compare three municipal projects from the City of Cape Town:
- The 2010 FIFA Integrated Transport implementation — IRT.
- The Athlone mass vaccination centre — COVID-19.
- The Bus Rapid Transit implementation in Imizamo Yethu — BRT.
The first two projects achieved their objectives, whereas the third was terminated following strong community resistance.
The analysis draws on interviews, workshops, project documents and secondary sources. Recurring patterns were coded and consolidated into five drivers of stakeholder complexity.
2010 FIFA Integrated Transport Implementation
Cape Town introduced a new bus system in preparation for the 2010 FIFA World Cup. The project threatened the income of existing taxi and bus operators.
A separate project stream was established to work with these stakeholders. Engagement included negotiations, alternative income arrangements and pension packages intended to reduce the negative economic consequences of the new system.
Athlone Mass Vaccination Centre
The Municipality, Provincial Government, healthcare organisations and facility operators created a large vaccination centre within a few months.
The project had a clear public objective, strong institutional support and predominantly role-based stakeholders with defined authority and responsibilities.
Bus Rapid Transit in Imizamo Yethu
The introduction of the MyCiTi bus service reduced demand for local taxis and affected drivers, mechanics, fare collectors, traders and others dependent on the taxi economy.
Stakeholders considered the consultation process inadequate. A proposed bus turnaround facility generated community opposition, political conflict and threats of violence. The project was eventually cancelled because of safety concerns.
Why Stakeholder Composition Matters
The decisive factor was not simply the number of stakeholders but their composition.
The COVID-19 project was dominated by role-based stakeholders. Responsibilities were clear, and coordination relied on structured meetings, direct communication and established decision-making authority.
IRT and BRT involved numerous agenda-based stakeholders, including taxi associations, community leaders and political groups. IRT engaged these groups in developing the solution and building trust. BRT mainly communicated decisions without enabling meaningful participation.
The larger the proportion of agenda-based stakeholders, the greater the need for negotiation, relationship-building and adaptation.

Power, Legitimacy and Urgency
The article analyses stakeholder power through the salience model:
- Power: the ability to affect project outcomes.
- Legitimacy: the recognised right to participate or make claims.
- Urgency: the immediacy of stakeholder demands.
In the COVID-19 project, power was institutional and supported rapid decision-making. In IRT, the influence of taxi operators was recognised and incorporated into negotiations.
In BRT, the informal power of taxi associations was underestimated. These groups mobilised the community and ultimately helped stop the project.
Stakeholder power is therefore not determined solely by formal position. It also depends on the ability to allocate resources, shape perceptions, organise support or create resistance.
Social Justice and Politics
The IRT and COVID-19 projects considered fairness from the beginning. The Athlone centre was expected to provide service at least equal to that available in wealthier parts of the city. In IRT, the government attempted to ensure that existing transport operators would not become economically worse off.
In BRT, the relocation of nine families into new housing was perceived as unfair by other residents who remained on waiting lists. The project also became associated with conflict between political parties.
The article distinguishes between:
- Distributive justice: who receives the benefits and bears the costs.
- Procedural justice: who participates and how decisions are made.
Ignoring either dimension can undermine trust and project legitimacy.
Informal Networks of Influence
Influence is transmitted through both formal and informal relationships.
In IRT, the City worked with taxi association leaders who could influence large groups of operators. In the COVID-19 project, local media acted as trusted intermediaries between the project and the public.
In BRT, the community and professional networks of the taxi industry proved stronger than the project’s official communication channels.
Project managers must therefore identify not only who has influence, but also who can influence other influential stakeholders.

Project Characteristics
Goal clarity, public value, schedule constraints and governance arrangements can either increase or reduce stakeholder complexity.
IRT and COVID-19 had clear objectives connected to widely recognised public interests. In BRT, the project’s purpose was poorly communicated and did not align with the community’s immediate priorities.
Time constraints also limit engagement. Restricted consultation was acceptable in the emergency COVID-19 project because rapid implementation was the dominant success criterion. In BRT, however, success depended on local stakeholder acceptance, but the governance and schedule did not provide sufficient time or flexibility to secure it.
Five Drivers of Stakeholder Complexity
The study identifies five interconnected drivers of stakeholder complexity:
- Stakeholder mix.
- Power, legitimacy and urgency.
- Social justice and politics.
- Influence networks.
- Project characteristics.
These factors do not operate independently. Perceived injustice becomes more disruptive when supported by powerful stakeholder networks. Rigid governance and schedules increase conflict when successful delivery depends on the consent of agenda-based stakeholders.
Stakeholder complexity should therefore be understood as a dynamic and systemic property of the project, changing over time as interests, relationships, legitimacy and power evolve.
Early Engagement, Trust and Adaptation

IRT and COVID-19 succeeded because stakeholder relationships were recognised and managed early. BRT failed primarily because the project did not adequately engage influential agenda-based stakeholders whose cooperation was essential.
Stakeholder management should therefore include continuous interpretation, adaptation and scenario planning rather than only an initial stakeholder register.
Practical Management Implications
For role-based stakeholders, suitable tools include:
- RACI matrices;
- governance and decision-making structures;
- communication plans;
- defined reporting channels.
For agenda-based stakeholders, project managers need:
- political and social analysis;
- negotiation and trust-building;
- assessment of informal influence;
- understanding of perceived fairness;
- greater flexibility in the proposed solution.
Highly complex initiatives may benefit from being managed as programmes, with separate workstreams and appropriately skilled managers for technical delivery and stakeholder engagement.
Limitations and Further Research
The study covers only South African municipal infrastructure projects, so its conclusions may not transfer directly to corporate or technology projects. One of the three cases was also based mainly on secondary evidence.
Further research should examine how stakeholder power, legitimacy and influence change over time and why formal stakeholder analysis models remain underused or superficially applied in practice.